The EDAR's control
is organized at two CCMs. One ABB's CPU KT94 is placed at
each CCM. Every CPU has connected a number of analog, digital,
input and output cards through bus cs31.
Each one communicates directly with the computer's control
(SCADA) by RS485's series line, using MODBUS protocol.
CPUs are connected inwardly using ARC-NET, by this way,
they can exchange signals directly and know element's status
of the other CCM.
Every remote stations is equipped with a CPU KT94, with
his own control program able to manage the EBAR if it becomes
lonely, that is to say that it don't have communication
with EDAR.
|